|
ENGINEERING
& DEVELOPMENT
(770) 387-5170; Menu Option 3
Development
Procedures
The planning,
design and construction of
water and wastewater utility
systems for residential, commercial and industrial developments must be
thoroughly analyzed, reviewed and inspected by our Engineering &
Development Department to verify their accordance with established
development
procedures, specifications, requirements, local ordinances, Bartow
County
Growth Management Plan and all other applicable guidelines prior to
final
approval and connection with the Bartow County Water & Sewer
System. A
Developer (or authorized representative thereof) must submit a formal
written
request to the Bartow County Water Department regarding water and/or
sewer
service availability at or near their proposed development. A $105.00 Flow
Test Fee shall be submitted upon ordering a water system flow
test that
will be conducted upon the water service main closest to the proposed
development for the purposes of calculating current water system
pressure and
flow rates to officially determine water service availability status.
Based
upon the results of the water system flow test, the Developer’s
Engineer must calculate
the availability of water required to meet peak domestic service
demands and
fire protection for the proposed development. The water utility system
shall be
designed to maintain a minimum pressure of 30 p.s.i. (pounds per square inch)
at each water service connection and all associated distribution points
under
peak domestic demand and fire flow. The Developer’s Engineer must provide a
comprehensive report based upon these results detailing the
construction
purpose, average daily water consumption and peak demands calculated to
service
the proposed development, certifying that connection of said
development to the
Bartow County Water System shall not produce unacceptable fire flow
levels.
Fire flows for commercial and industrial developments shall be no less
than
1,000 g.p.m.; multi-family residential no less than 750 g.p.m.;
single-family
residential no less than 500 g.p.m.. (Note:
For low-density developments, lower fire flows may be acceptable based
upon the
risk to adjoining properties as determined by the acting Bartow County
Fire
Chief.) The developer must provide our department three (3)
complete
sets of construction plans for the proposed development detailing the
geographic location, development layout and conceptual design of
proposed water
and/or sewer utility services with separate plans for both water and
sewer. A $160.00 Plan
Review Fee shall be submitted for each set of plans
or each
new version of plans reviewed including preliminary plans, construction
plans
and as-builts (final plans). Development plans submitted to Bartow County for approval must also be accompanied by a
letter
signed by a Georgia Registered Engineer confirming that there is not a
landfill
on the site of the proposed development:
Pursuant to
Act 599, “The Erosion and Sedimentation Act”: “Therefore, effective
immediately, all utility plans submitted to the Division for
environmental
approval, as required by State regulations, must include defined
contract
requirements for erosion and sedimentation control. Requirements for
erosion
and sedimentation control should be defined such that costs may be
included in
the bid proposal. Please note, however, that any required erosion and
sediment
control plan must still be approved by the Soil and Water Conservation
District. If the Environmental Protection Division is the permitting
authority
for the land-disturbing permit for the specific project, a thirty (30)
day
public notice will be required. All local jurisdictions with delegated
environmental approval responsibilities should be guided accordingly in
the
development and approval of construction water and sewer project plans."
The
proposed project will be reviewed by the Bartow County Water Department
and, if
approved, one (1) copy of the approved plan shall be returned to the
developer
for construction purposes. The Developer shall schedule a
pre-construction
conference with his Contractor and the Bartow County Water Department
to
coordinate project construction schedules including making bores,
installing
taps, connecting to existing service lines, arranging for the
acquisition of
all necessary permits, etc. (Note:
Contractors must possess a valid Georgia Utilities Contractor License
and be
formally approved by the Bartow County Water Department.) The
Contractor shall then provide the Bartow County Water Department with a
certified copy of his quote for the particular project. Prior to
initial
construction authorization of the project, a $655.00 Tap-On Fee per each water
service main connection and an Inspection Fee,
equivalent to 2%
of projected Construction Cost, shall be submitted. (Note:
Confirmation of the final contract total may be required
before approval shall be granted for the project.) Also, water
usage
for filling and flushing will be billed at $4.50 per thousand gallons
based
upon a minimum of four (4) times the volume of the pipe. [Example:
5000 LF 8” pipe X 2.89 gallons/ft. X $4.50/thousand
gallons X 4 = $260.10.] The Contractor must adhere to the
Specifications of the Bartow County Water Department per materials used
and
methods of installation. During periods of construction the Developer
and/or
Contractor shall be responsible for installing locate flags, painting
the curb
at all road crossings, short-side taps and maintaining same until all
service
utilities are installed and completed. Should access to any new
development
cross or cover an existing PVC water service main, then the Developer
shall be
responsible for relocating the affected service line or replacing it
with
ductile iron piping (DIP). The Contractor will be required to
periodically
update the Bartow County Water Department regarding construction
progress of
the project so mandatory inspections can be scheduled and conducted.
Due to
past problems with ditches settling the Bartow County Water Department,
at its
own discretion, may require that compaction tests be performed by a
reputable
firm at the Developer’s expense to assure proper compaction has been
achieved.
Prior to the installation of water meters within a development, all
required
water utility system tests shall be conducted and passed per Bartow
County
Water & Sewer System Specifications while any applicable property
deeds
and/or utility easements shall be executed and properly recorded.
As-built
drawings shall be submitted to the Bartow County Water Department along
with a
$160.00 Plan
Review Fee detailing the
exact location of all water utility infrastructure including service
lines,
service taps, valves and fire hydrants. These as-built drawings shall
be produced
by the Engineer of Record for the project and presented on two (2)
complete
sets of fresh drawings. The Engineer of Record must also certify upon
the
as-built drawings that they (or designated representative thereof under
their
direct supervision) have made sufficient visits to the project site
confirming
the said development was constructed according to Plans and
Specifications as
approved. A final inspection shall then be conducted by the Bartow
County Water
Department to assure that these as-built drawings are accurate and that
all
meter setters and boxes have been properly installed. Once all required
maintenance procedures indicated during this final inspection have been
successfully completed by the Contractor and accepted by the Bartow
County Water
Department, final approval shall be granted for the project. (Note: If a water meter cannot be
properly seated, an additional charge shall be made for adjustments
performed
to the setters and/or box or any repairs to the same.) The Developer shall be solely responsible for
all water and/or sewer system repairs performed within the development
for a
period of one (1) year from the date of final project approval. Should
a leak
or blowout occur during the required one-year warranty period, the
Developer shall
be responsible for all necessary repairs, estimated water loss,
retesting of
the utility system and reimbursement of any associated expenses
incurred by the
Bartow County Water Department.
Bartow
County Water & Sewer System Specifications

Bartow
County Standard Specifications for Water & Sewer Construction
Bartow
County Water & Sewer Site and Utility Details for Development
Bartow
County Water System Development Procedures
Bartow
County Water Service Main Installation Specifications
Bartow
County Water Meter Vault Specifications
Bartow
County Sewer Service Development & Installation Specifications
Bartow
County Sanitary Sewer Systems Inspection & Testing Procedures
Development
Fees
The
following Development Fees must be
paid prior to final approval and connection with the
Bartow County
Water &
Sewer System. (Note: Additional charges may be required!)
Flow Test Fees
- $105.00 per Flow Test.
Plan Review Fees
- $160.00 per each new set of
plans or each new revision of plans reviewed including preliminary
plans, construction
plans and as-builts (final plans).
Tap-On
Fees - $655.00 per service main connection.
Inspection
Fees - 2% of total development
construction costs per the Contractor’s certified quote.
Readiness-to-Serve
Fees* - Readiness-to-Serve
Fees are comprised of two (2)
separate fees for each service including a Water
Capacity Fee and a Water Distribution
& Transmission Fee for water service and a Wastewater
Capacity Fee and a Wastewater
Collection Fee for sewer service. Water
Distribution & Transmission Fees are determined based upon the
greater
amount of either: A) $655.00 per Equivalent
Dwelling Unit (E.D.U.), equal to approximately 350 Gallons per Day
(G.P.D.) as detailed
within the “Bartow County Water Department Structural Daily Water
Usage
Schedule” or B) The applicable Water
Distribution & Transmission Fee
indicated within the “Water Service Readiness-to-Serve Rate Table”
below. Wastewater Collection Fees are
determined based upon the greater amount of either: A)
$760.00 per Equivalent Dwelling Unit (E.D.U.) or B) The applicable Wastewater
Collection
Fee indicated within the “Sewer Service Readiness-to-Serve Rate
Table
below. Water & Sewer Capacity Fees
are determined based upon the greater amount of either:
A)
The Water and Sewer Capacity Fees indicated
within the Water & Sewer Service
Readiness-to-Serve Rate Tables below or B)
The amount calculated when multiplying the number of units by $1,125.00
for
water service and by $1,375.00 for sewer service.
| Water
Service Readiness-to-Serve Rate Table |
| Meter Size |
Water Capacity Fee |
Water Distribution
& Transmission Fee |
Total
Readiness-to-Serve Fee |
| 5/8” x ¾” |
$1,125.00 |
$655.00 |
$1,780.00 |
| 1" |
$2,810.00 |
$1,635.00 |
$4,445.00 |
| 1 ½” |
$5,620.00 |
$3,275.00 |
$8,895.00 |
| 2” |
$8,995.00 |
$5,240.00 |
$14,235.00 |
| 3” |
$17,995.00 |
$10,480.00 |
$28,475.00 |
| 4” |
$28,120.00 |
$16,380.00 |
$44,500.00 |
| 6” |
$56,235.00 |
$32,760.00 |
$88,995.00 |
| 8” |
$89,980.00 |
$52,415.00 |
$142,395.00 |

| Sewer
Service Readiness-to-Serve Rate Table |
| Meter Size |
Sewer Capacity Fee |
Wastewater Collection
Fee |
Total
Readiness-to-Serve Fee |
| 5/8” x ¾” |
$1,375.00 |
$760.00 |
$2,135.00 |
| 1" |
$3,440.00 |
$1,910.00 |
$5,350.00 |
| 1 ½” |
$6,880.00 |
$3,820.00 |
$10,700.00 |
| 2” |
$11,005.00 |
$6,115.00 |
$17,120.00 |
| 3” |
$22,015.00 |
$12,230.00 |
$34,245.00 |
| 4” |
$34,395.00 |
$19,110.00 |
$53,505.00 |
| 6” |
$68,795.00 |
$38,220.00 |
$107,015.00 |
| 8” |
$110,075.00 |
$61,150.00 |
$171,225.00 |
*Note:
Water Distribution & Transmission Fees and Wastewater Collection
Fees are not appliable to residents that have owned serviceable parcels
prior to October 6, 1993 according to the Bartow County Water &
Sewer Rate Structure and Readiness-to-Serve Ordinance adopted December
9, 2005 providing proof of ownership is presented during new service
application procedures.
Bartow County has become one of the most rapidly
developing
political subdivisions in the State of Georgia. According to the 2000 United States Census,
our
population exceeds 76,000 residents, reflecting a substantial increase
of approximately
36% during the past decade. Residential, commercial and industrial
developments
established in response to this continued growth have placed vigorous
construction
and service demands upon every local utility provider including the
Bartow
County Water & Sewer Department. Within the last five (5) years,
the total
number of Bartow County Water & Sewer System serviced customers has
increased
by 115%, resulting in a current system-wide water consumption average
of approximately
6.5 M.G.D. (Million Gallons per Day). The Bartow County Government
recently
obtained the professional services of economic advisors, certified
auditors and
engineering firms to conduct a series of financial evaluations, system
infrastructure analyses, environmental surveys and resource
availability
studies in formulating the most productive and cost-efficient solutions
to
successfully manage the impacts of continued growth upon our local
communities.
The information collected and resolutions discovered from this
extensive period
of research are detailed within the Bartow County Growth Management
Plan
© February 7, 1997. Monetary funding required for the construction of
water and
wastewater system expansion projects deemed essential within this
publication
are currently provided to our department through several financial
resources
including metered water sales; corporate and private grants; short-term
loans
and capital collected through the Special Purpose Local Option Sales
Tax
(S.P.L.O.S.T.) Program successfully voted into Bartow County law during
the June
19, 2007 Election that is projected to provide our utility system with
an additional
$31.35 million of operational and construction revenue through 2007.
Projects
associated with this program include: Glade Road Area Collection
Sewers, Pump
Station & Force Main; Southeast Bartow County Waste Water Treatment
Plant;
State Route 113 12” & 16” Water Mains; Woodland School Sewer Pump
Station
Replacement & Force Main; Camden Woods Subdivision Collection
Sewers;
Founders Grove Subdivision Trunk & Collection Sewers; Cassville
Area
Collection Sewers; Two Run Creek Trunk Sewer, Force Main &
Treatment Plant;
Kingston Collection Sewers; Ivy Chase Subdivision Collection Sewers;
Peeples
Valley Road 3 Million Gallon Water Reservoir; Saddlebrook Subdivision
&
Greystone Subdivision Collection Sewers; Willow Bend Subdivision
Collection
Sewers; Highway 411/Interstate-75 Interchange Crossing 12” Water Main
Replacement; Zion Road Water & Sewer System Improvements; Mosteller
Road
& East Pleasant Valley Road 8” Water Mains; Maxwell Road, Old
Tennessee
Road & Olive Vine Church Road 8” Water Mains; Cagle Road 8” Water
Main;
State Route 20 Sewer Line Replacement; and Holly Springs Road 12” Water
Main. For
additional information regarding these projects, please contact Mr.
Roger
Ellis; Bartow County Water Department Engineering & Project Manager
@ (770)
387-5169.
Geographic
Information System (G.I.S.)
The
development and implementation of technological advancements have
become the most instrumental and effective methods utilized for
efficient
growth-management planning solutions within government agencies,
corporations, industrial
manufacturers, utility systems, and other public service providers
throughout
the world. The Bartow County Government and its associated
administrative
departments have invested a substantial amount of financial resources
and
personnel hours toward the establishment and daily operation of a
Geographic
Information System (G.I.S.). This comprehensive electronic mapping
software application
has effectively consolidated the environmental, hydrological,
agricultural,
demographical, parcel ownership and utility infrastructure features of Bartow County within an exclusive intergovernmental
database. The
Bartow County Water Department contracted the digital mapping expertise
of
Sanborn Colorado, L.L.C. ® headquartered in Colorado Springs, Colorado to assist with the conversion of over 900
water and
wastewater utility system sources into G.I.S. coordinate-based digital
renderings.
Additional residential, commercial and industrial development mapping
sources
are routinely submitted to Mactec Engineering and Consulting
headquartered in Warner Robins, Georgia for digital conversion to ensure our utility
system
infrastructure has been represented in an accurate and timely manner.
This
exceptionally beneficial software application has permitted our
department to
successfully design more cost-efficient construction plans and
procedures;
reduce utility service outage response times; perform immediate
infrastructure
locates and provide vital water and wastewater system information to
our
customers, maintenance & operations personnel, developers,
engineers,
contractors, local utility providers, corporation, industrial
manufacturers, etc.
and shall continue to provide our organization and other Bartow County
Government administrative departments with unprecedented operational
capabilities. For additional information regarding the Bartow County
Water
Department Geographic Information System (G.I.S.), please contact Mr.
Michael
Yancey; M.I.S./Administrative Assistant @ (678) 721-5489, Mr. Bryan St.
Mary,
Bartow County Government G.I.S. Technician @ (770) 607-6184 or Mrs.
Robin
Puryear; Bartow County Government Information Systems Manager @ (770)
607-6358.
|